Dehradun
|
|
S.No
|
Project
|
Project Cost
|
|
1
|
Khala Basti Slum, Dehradun
|
372.83
|
|
2
|
Kanthbungala Slum, Dehradun
|
622.93
|
|
3
|
Dpr For Rotary Kussthrog Ashram, Dehradun
|
163.34
|
|
4
|
Dpr For Shanti Lusth Ashram (Main Basti) Dehradun
|
137.2
|
|
5
|
Dpr For Ram Mandir Kusth Ashram (Malin Basti) Dehradun.
|
163.64
|
|
6
|
Dpr For Chaksha Nagar Slum (Malin Basti)
|
860.2
|
|
7
|
240 Dus Slum Upgradation Of Niranjanpur, Barhmpuri, Phase-1 Dehradun, State Of Uttrakhand
|
1114.66
|
|
8
|
224 Dus Bsup Dpr For Ram Nagar Slum (Main Basti), Dehradun, State Of Uttrakhand
|
1159.88
|
|
9
|
421 Dus Dpr For Slum Upgradation Of Niranjanpur, Barhmpuri, Phase-Ii, Dehradun, State Of Uttrakhand
|
1667.31
|
| |
|
|
|
1
|
Project-1
|
|
| |
Project title
|
Khala Basti Slum, Dehradun
|
|
Scheme
|
BSUP
|
|
Sanctioned Project Cost(INR in Lakhs)
|
372.83
|
|
Project Duration(in Months)
|
24
|
|
Appraisal Agency
|
BMTPC
|
|
SLNA
|
Uttaranchal
|
|
City
|
Dehradun
|
|
Approved Date
|
12/20/2007
|
|
No. of DUs sanctioned
|
80
|
|
GoI share
|
290.92
|
| |
|
|
2
|
Project-2
|
|
| |
Project title
|
Kanthbungala Slum, Deharadun
|
|
Scheme
|
BSUP
|
|
Sanctioned Project Cost(INR in Lakhs)
|
622.93
|
|
Project Duration(in Months)
|
15
|
|
Appraisal Agency
|
BMTPC
|
|
SLNA
|
Uttranchal
|
|
City
|
Dehradun
|
|
Approved Date
|
12/20/2007
|
| |
No. of DUs sanctioned
|
148
|
|
GoI share
|
485.016
|
| |
|
|
| |
Project-3
|
|
| |
Project title
|
Dpr For Rotary Kussthrog Ashram, Dehradun
|
|
Scheme
|
BSUP
|
|
Sanctioned Project Cost(INR in Lakhs)
|
163.34
|
|
Project Duration(in Months)
|
15
|
|
Appraisal Agency
|
BMTPC
|
|
SLNA
|
Uttranchal
|
|
City
|
Dehradun
|
|
Approved Date
|
1/30/2009
|
|
No. of DUs sanctioned
|
34
|
|
GoI share
|
115.928
|
| |
|
|
| |
Project-4
|
|
| |
Project title
|
Dpr For Rotary Kussthrog Ashram, Dehradun
|
|
Scheme
|
BSUP
|
|
Sanctioned Project Cost(INR in Lakhs)
|
137.2
|
|
Project Duration(in Months)
|
15
|
|
Appraisal Agency
|
BMTPC
|
|
SLNA
|
Uttranchal
|
|
City
|
Dehradun
|
|
Approved Date
|
1/30/2009
|
|
No. of DUs sanctioned
|
28
|
|
GoI share
|
109.76
|
| |
|
|
| |
Project-5
|
|
| |
Project title
|
Dpr For Rotary Kussthrog Ashram, Dehradun
|
|
Scheme
|
BSUP
|
|
Sanctioned Project Cost(INR in Lakhs)
|
163.64
|
|
Project Duration(in Months)
|
15
|
|
Appraisal Agency
|
BMTPC
|
|
SLNA
|
Uttranchal
|
|
City
|
Dehradun
|
|
Approved Date
|
1/30/2009
|
|
No. of DUs sanctioned
|
27
|
| |
GoI share
|
111.798
|
| |
|
|
| |
Project-6
|
|
| |
Project title
|
Dpr For Chaksha Nagar Slum (Malin Basti)
|
|
Scheme
|
BSUP
|
|
Sanctioned Project Cost(INR in Lakhs)
|
860.2
|
|
Project Duration(in Months)
|
15
|
|
Appraisal Agency
|
BMTPC
|
|
SLNA
|
Uttranchal
|
|
City
|
Dehradun
|
|
Approved Date
|
1/30/2009
|
|
No. of DUs sanctioned
|
160
|
|
GoI share
|
655.054
|
| |
|
|
| |
Project-7
|
|
| |
Project title
|
240 Dus Slum Upgradation Of Niranjanpur, Barhmpuri, Phase-1 Dehradun, State Of Uttrakhand
|
|
Scheme
|
BSUP
|
|
Sanctioned Project Cost(INR in Lakhs)
|
1114.66
|
|
Project Duration(in Months)
|
18
|
|
Appraisal Agency
|
BMTPC
|
|
SLNA
|
Uttranchal
|
|
City
|
Dehradun
|
|
Approved Date
|
2/8/2010
|
|
No. of DUs sanctioned
|
240
|
|
GoI share
|
876.14
|
| |
|
|
| |
Project-8
|
|
| |
Project title
|
224 Dus Bsup Dpr For Ram Nagar Slum (Main Basti), Dehradun, State Of Uttrakhand
|
|
Scheme
|
BSUP
|
|
Sanctioned Project Cost(INR in Lakhs)
|
1159.88
|
|
Project Duration(in Months)
|
18
|
|
Appraisal Agency
|
BMTPC
|
|
SLNA
|
Uttranchal
|
|
City
|
Dehradun
|
|
Approved Date
|
1/27/2010
|
|
No. of DUs sanctioned
|
224
|
|
GoI share
|
853.87
|
| |
|
|
| |
Project-9
|
|
| |
Project title
|
421 Dus Dpr For Slum Upgradation Of Niranjanpur, Barhmpuri, Phase-Ii, Dehradun, State Of Uttrakhand
|
|
Scheme
|
BSUP
|
|
Sanctioned Project Cost(INR in Lakhs)
|
1667.31
|
|
Project Duration(in Months)
|
18
|
|
Appraisal Agency
|
BMTPC
|
|
SLNA
|
Uttranchal
|
|
City
|
Dehradun
|
|
Approved Date
|
3/5/2010
|
|
No. of DUs sanctioned
|
421
|
|
GoI share
|
1305.94
|